Rich Construction Company Community Centre Project
Project Type: Infrastructure
In March 2025, Rich Construction Company undertook a Community Centre project requiring the simultaneous operation of 4 tower cranes (36ton) and its site block power. Although grid power was available, the high and fluctuating power demands during peak construction hours posed challenges in maintaining energy stability, efficiency, and cost control. A smart energy solution was needed to optimise power usage, reduce peak load stress on the grid, and support sustainable site operations.
Project Requirements
x4 Tower Cranes (36T), Site Block Power
Project Results
By replacing four large 600kVA diesel generators with Infinity Cube’s Charging BESS System, comprising of just four compact Infinity Cube M units charged directly from the grid, Rich Construction Company eliminated the need for four large diesel generators on site. The result was a dramatic cut in annual diesel consumption delivering major cost savings while significantly lowering carbon emissions.